Construction, completed in 2025, consisted of a mix of concrete, steel and timber construction with a mix of deep piled foundations and ground improvement.  Construction was carried out in multiple overlapping stages on a compact central city building site.  Special foundation provisions were required for buildings flanking a critical easement for power supply which passes through the site.